Construction History
March 2012

February 2012

January 2012

December 2011

November 2011

October 2011

September 2011

August 2011

July 2011
June 2011 Report
- Carpentry and joinery works are 80% completed.
- MEP works (electrical, mechanical, drainage, water supply) 96% completed and in progress.
- A/C works 98% completed.
- Lift works 94% completed.
- Aluminum and glass works 95% completed. (Windows and doors).
- Curtain wall for the outside façade is 98% completed.
- Tile works has started up to the 18th floor with an average of 75% completed.
- The removal of the tower carne started on 25/6/2011; it will take 5 days to be completely dismantled.
- The removal of the scaffolding will start on 28/06/2011; it will take one week to two weeks to get it all cleared.
May 2011 Report
- 100% of the sub-structure is complete.
- 100% of super-structure is complete.
- 100% of all block work is complete
- 98% of the outside façade curtain walling is complete.
- 98% of air conditioning works are now complete
- 94% of the lift machinery and associated lift works is complete.
- 94% of MEP work (electrical, mechanical, drainage, water supply) is now complete with work in progress in 9th to 18th floor.
- 95% of aluminium and glass works for the windows and doors is complete.
- Carpentry and joinery works are 55% completed.
- Tiling work is in progress up to the 16th floor with an average of 85% completed.
April 2011 Report
- 100% of the sub-structure is complete.
- 100% of super-structure is complete.
- 100% of all block work is complete
- 98% of the outside façade curtain walling is complete.
- 98% of air conditioning works are now complete
- 94% of the lift machinery and associated lift works is complete.
- 94% of MEP work (electrical, mechanical, drainage, water supply) is now complete with work in progress in 9th to 18th floor.
- 95% of aluminium and glass works for the windows and doors is complete.
- Carpentry and joinery works are 55% completed.
- Tiling work is in progress up to the 16th floor with an average of 67% completed.
March 2011 Report
- 100% of the sub-structure is complete.
- 100% of super-structure is complete.
- 100% of all block work is complete
- 98% of the outside façade curtain walling is complete
- 98% of air conditioning works are now complete
- 94% of the lift machinery and associated lift works is complete
- 90% of MEP work (electrical, mechanical, drainage, water supply) is now complete with work in progress in 9th to 18th floor.
- 90% of aluminium and glass works for the windows and doors is complete.
- Carpentry and joinery works are 49% completed.
- Tiling work is in progress up to the 16th floor with an average of 55% completed.
February 2011 Report
- 100% of the sub-structure is complete.
- 100% of super-structure is complete.
- 100% of all block work is complete
- 98% of the outside façade curtain walling is complete.
- 96% of air conditioning works are now complete
- 94% of the lift machinery and associated lift works is complete.
- 90% of aluminium and glass works for the windows and doors is complete.
- 84% of MEP work (electrical, mechanical, drainage, water supply) is now complete with work in progress in 9th to 18th floor.
- Carpentry and joinery works are 38% completed.
- Tiling work is in progress up to the 14th floor with an average of 48% completed
January 2011 Report
- 100% of the sub-structure is complete.
- 100% of super-structure is complete.
- 100% of all block work is complete
- 98% of the outside façade curtain walling is complete.
- 94% of air conditioning works are now complete
- 90% of the lift machinery and associated lift works is complete.
- 90% of aluminium and glass works for the windows and doors is complete.
- 79% of MEP work (electrical, mechanical, drainage, water supply) is now complete with work in progress in 9th to 18th floor. • Carpentry and joinery works are 35% completed.
- Tiling work is in progress up to the 12th floor with an average of 45% completed
December 2010 Report
- 100% of the sub-structure is complete.
- 100% of super-structure is complete.
- 100% of all block work is complete.
- 100% of plastering work is complete.
- 95% of the outside façade curtain walling is complete.
- 92% of air conditioning works are now complete.
- 90% of the lift machinery and associated lift works is complete.
- 85% of aluminium and glass works for the windows and doors is complete.
- 75% of air conditioning works are now complete with work in progress in floors 9 to 18.
- Carpentry and joinery works are 35% completed.
- Tiling work is in progress up to the 6th floor
November 2010 Report
- 100% of the sub-structure is complete.
- 100% of super-structure is complete.
- 100% of all block work is complete.
- 100% of plastering work is complete.
- 95% of the outside façade curtain walling is complete.
- 90% of the lift machinery and associated lift works is complete.
- 85% of aluminium and glass works for the windows and doors is complete.
- 75% of air conditioning works are now complete with work in progress up to the 18th floor.
- 75% of the MEP works (electrical, mechanical, drainage, water supply) are complete and in progress between 9th – 18th floor.
- 10% of carpentry and joinery works are complete.
October 2010 Report
- 100% of the sub-structure is complete.
- 100% of super-structure is complete.
- 100% of all block work is complete.
- 100% of plastering work is complete to the 14th floor and well advanced between 15th and 18th floors
- 95% of the outside façade curtain walling is complete and the balance is expected to be finished by mid October.
- 85% of lift machinery and associated lift works installation is complete.
- 85% of aluminium and glass works for the windows and doors is complete.
- 85% of air conditioning works are now complete with work in progress up to the 18th floor.
- 70% of MEP works (electrical, mechanical, drainage, water supply) are completed and in progress from 9th to 18th floors.
September 2010 Report
- 100% of the sub-structure is complete.
- 100% of super-structure is complete.
- 100% of all block work is complete.
- 90% of all plastering work is complete.
- 90% of the outside façade curtain walling is complete and the balance is expected to be finished by mid October.
- 85% of drainage and water piping is complete.
- 85% of lift machinery and associated lift works installation is complete.
- 68% of aluminium and glass works for the windows and doors is complete.
- 45% of air conditioning works are now complete with work in progress in the 12th floor.
- 30% of all electrical are now complete with work in progress in the 12th floor.
August 2010 Report
- 100% of the block works are completed.
- The plastering work is done up to the 8th floor and in progress in the 9th.
- The curtain walling is 85% completed.
- Drainage and water piping is 85% completed.
- AC works are 90% completed.
- Electrical works and wiring are 35% complete.
July 2010 Report
- 100% super structure completed.
- The curtain walling is in progress;
- 70% on the front elevation
- 90% on the rear elevation
- 80% for the side elevations - Air Conditioning works are completed up to 12th floor.
- Electrical wiring works are completed up to 5th floor.
- Plaster works are completed up to 5th floor.
June 2010 Report
- 100% super structure completed.
- Curtain walling progress as follows;
- 70% for the front elevation,
- 90% for the rear elevation
- 80% for the side elevations. - Expected completion for the curtain walls’ by August.
- The Air Conditioning work completed up to 12th floor.
- Electrical wiring completed up to 5th floor.
- The plaster work completed up to 5th floor.
- Two show flats will be ready by the end of June.
May 2010 Report
- 100% of super structure has been completed.
- The curtain walling is in progress;
70% completed on the front;
90% completed on the back; and
80% completed on the sides. - The MEP, AC and fire fighting system works are in progress.
- The plaster work has commenced on the 3rd floor.
April 2010 Report
- All structural work is complete.
- The curtain walling is in progress; 65% for the front side, 90% for the back side and 80% for the sides.
- The MEP, AC and fire fighting works are in progress.
- The plaster work has started in the 2nd floor.
* Please note that the details of construction progress for this development are largely provided to us by the project consultants and contractors. Any reference to future construction milestone dates is in accordance with their reports to us and The First Group are unable to accept responsibility for any errors.