Construction Status

August Report

  • Block work have been completed in the whole building.
  • Plastering is complete up to the 16th floor.
  • Tiling works for the walls are completed and flooring is up to 14th floor.
  • Air conditioning works are close to completion with all ducting and piping work completed and the final fixing of the fittings are in progress.
  • The electrical works and wiring are completed; the LV panel is balance and expected to be completed within 30 days.
  • Drainage and water supply piping have been completed 100%.
  • False ceiling inside the units are completed up to the 14th floor and in the corridors is up to the 6th floor.
  • The curtain wall works are completed for the whole building; the capping of the curtain walls is kept open for the wiring required for the external lighting of the building; this is expected to be completed by the end of this month.
  • Lifts have been installed
  • The final rendering and design for the main lobby, health club and common areas has been completed by John R Harris and Partners (JRHP).

July Report

  • 100% super structure completed.
  • Plastering works are completed up to the 14th floor.
  • The MEP conduit works are completed up to the 15th floor.
  • The tiling works for the walls are completed up to the 13th floor.
  • Wall ceramic tiling works are completed up to the 10th floor
  • Cladding works are 75% complete
  • The curtain walls are scheduled for completion by end of July 2010.

June Report

  • 100% super structure completed.
  • Plastering works completed up to the 14th floor.
  • The MEP conduit works in progress at the 15th floor.
  • The wall tiling works are complete up to the 13th floor.
  • The curtain wall works are completed to the 10th floor and 75% of the cladding erection is complete, the curtain walls should be completed by 31st July.

May Report

  • 100% of super structure has been completed.
  • Plastering works are up to the 14th floor.
  • The MEP conduit works in progress at the 15th floor.
  • The tiling works for the walls have reached up to the 13th floor.
  • The curtain walls' works are in progress up to the 6th floor and the erection of the cladding works has reached 60%.

April Report

  • All block works have been completed throughout.
  • Plastering works are complete up to the 13th floor.
  • All the MEP conduit works are completed up to the 14th floor.
  • The tiling works are complete up to the 8th floor.
  • The curtain walls' works are in progress up to the 6th floor and 60% of the erection of the cladding work is finished


* Please note that the details of construction progress for this development are largely provided to us by the project consultants and contractors. Any reference to future construction milestone dates is in accordance with their reports to us and The First Group are unable to accept responsibility for any errors.