March 2012

The Bridge

February 2012

The Bridge

January 2012

The Bridge

December 2011

The Bridge

November 2011

The Bridge

October 2011

The Bridge

September 2011

The Bridge

August 2011

The Bridge

July 2011

The Bridge

June 2011 Report

    Civil Works

  • Aluminum Cladding = 87%
  • Tile works
  • Wet Area (Floors and Walls) = 97%
  • Dry Area
  • For office corridors floor (2nd – 8th) = 100%
  • Inside residential flats (12th – 30th) = 97%
  • False Ceiling = 95%
  • Wooden Doors = 30%
  • Paint inside flats = 40%
  • Lifts = 85% installed
  • Converted floors = 10%

    MEP Works:

  • Electrical Works = 80.1% completed
  • Plumbing Works = 90.1% completed
  • Fire Fighting Works = 80.3% completed
  • HVAC Works = 80.1% completed

May 2011 Report

  • 100% of sub structure is complete
  • 100% of super structure is complete
  • 100% of plastering work is complete
  • 100% of block work is complete
  • 97% of toilet wall tiling is completed up to 30th floor
  • 97% (on average ) of toilet floor tiling is completed from the 17th floor to the 30th floor
  • 95% of kitchen wall tiles completed up to 29th floor
  • 95 % of floor tiling completed up to 30th floor
  • 90% of corridor flooring completed in floors 2-7
  • 92% of corridor flooring completed in floors 12-28
  • False ceiling suspension and framing work completed from 12th floor up to 28th floor
  • 95% of gypsum board into false ceiling fixed up to 27th floor
  • 90% of wooden doors have been fixed up to 15th floor
  • 90% of garbage chute fixing is complete up to 31st floor
  • 95% of wet area waterproofing completed up to 30th floor
  • Primer and Stucco in progress in 31ST Floor
  • 70% of 1st coat painting to walls and 40% 1st coat painting to ceiling completed up to 17th floor
  • 95% of staircase terrazzo tiling completed in stair well 2 up to 31st floor.
  • 95% of staircase terrazzo tiling completed in stair well 1 up to 30th floor
  • 85% of staircase handrail fixing completed up to 30th floor in stair well 1
  • 90% of staircase handrail fixing completed up to 31st floor in stair well 2
  • Installation of commercial and Solo office lifts in progress
  • Installation of window cleaning equipment at roof floor in progress
  • 93% of drainage and water supply works completed up to the 28th floor and 50% completed between 29th & 31st floor
  • 90% of air conditioning works completed on average up to 31st floor
  • 87% of fire fighting system completed up to 30th floor
  • 80% of electrical works are completed up to the 30th floor

April 2011 Report

  • 100% of sub structure is complete
  • 100% of super structure is complete
  • 100% of plastering work is complete
  • 100% of block work is complete
  • 97% of toilet wall tiles completed up to 30th floor
  • Toilet floor tiles on average 97% completed from the17th floor to the 30th floor
  • 95% of kitchen wall tiles completed up to 29th floor
  • 93% of floor tiling completed up to 30th floor
  • False ceiling suspension and framing work completed from 14th floor to 28th floor
  • 95% of gypsum board into false ceiling fixed up to 25th floor
  • 80% of wooden doors have been fixed up to 14th floor
  • 90% of garbage chute fixing is complete up to 31st floor
  • 95% of wet area waterproofing completed up to 30th floor
  • Primer and Stucco in progress in 31st floor
  • 70% of 1st coat painting to walls and 40% 1st coat painting to ceiling completed up to 17th floor
  • 95% of staircase terrazzo tiling completed in stair well 2 up to 31st floor.
  • 95% of staircase terrazzo tiling completed in stair well 1 up to 30th floor
  • 85% of staircase handrail fixing completed up to 30th floor in stair well 1
  • 90% of staircase handrail fixing completed up to 31st floor in stair well 2
  • Installation of commercial and Solo office lifts in progress
  • Installation of window cleaning equipment at roof floor in progress
  • 93% of drainage and water supply works completed up to the 28th floor and 50% completed between 29th & 31st floor
  • 90% of air conditioning works completed on average up to 31st floor
  • 87% of fire fighting system completed up to 30th floor
  • 80% of electrical works are completed up to the 30th floor.

March 2011 Report

  • 100% of sub structure is complete.
  • 100% of super structure is complete.
  • 100% of plastering work has been completed up to 31st floor.
  • 100% of block work has been completed up to 31st floor.
  • 90% of toilet wall tiles completed up to 30th floor.
  • Toilet floor tiles on average 90% completed from the17th floor to the 30th floor.
  • 90% of kitchen wall tiles completed up to 29th floor.
  • 80% of floor tiling completed up to 30th floor.
  • 90% of false ceiling suspension and framing work completed up to 27th Floor.
  • 80% of gypsum board into false ceiling fixed up to 20th floor with 10% progress in 21st & 23rd floors.
  • 80% of wooden doors have been fixed up to 14th floor
  • 80% of garbage chute fixing is complete up to 31st floor.
  • 95% of wet area waterproofing completed up to 30th floor.
  • Paint primer and stucco in progress in 31ST Floor.
  • Primer and Stucco in progress in 31ST Floor.
  • 70% of 1st coat painting to walls and 40% 1st coat painting to ceiling completed up to 14th Floor.
  • 95% of staircase terrazzo tiling completed in stair well 2 up to 31st floor.
  • 95% of staircase terrazzo tiling completed in stair well 1 up to 30th floor.
  • 85% of staircase handrail fixing completed up to 28th floor in stair well 1.
  • 90% of staircase handrail fixing completed up to.
  • Installation of commercial and Solo office lifts in progress.
  • Installation of window cleaning equipment at roof floor in progress.
  • 93% of drainage and water supply works completed up to the 28th floor and 50% completed between 29th & 31st floor.
  • 90% of air conditioning works completed up to 29th floor and 30% completed in 30th floor 80% of fire fighting system completed up to 30th floor.
  • 70% of electrical works are completed up to the 29th floor.

February 2011 Report

  • 100% of sub structure is complete
  • 100% of super structure is complete
  • 100% of plastering work has been completed up to 31st
  • 100% of block work has been completed up to 31st floor
  • 80% of toilet wall tiles completed up to 29th floor
  • Toilet floor tiles completed up to 16th floor
  • 85% of kitchen wall tiles completed up to 28th floor
  • 70% of floor tiling completed up to 28th floor
  • 90% of false ceiling suspension and framing work completed up to 26th Floor
  • 70% of gypsum board into false ceiling fixed up to 16th floor
  • 80% of wooden doors have been fixed up to 14th floor
  • 80% of garbage chute fixing is complete up to 31st floor
  • 93% of wet area waterproofing completed up to 30th floor
  • Paint primer and stucco in progress in 31ST Floor
  • 70% of 1st coat painting to walls and 40% 1st coat painting to ceiling completed up to 14th Floor
  • 95% of staircase terrazzo tiling completed in stair well 2 up to 31st floor.
  • 95% of staircase terrazzo tiling completed in stair well 1 up to 30th floor.
  • 85% of staircase handrail fixing completed up to 13th floor in stair well 1
  • 85% of staircase handrail fixing completed up to 28th floor in stair well 2
  • Installation of commercial and Solo office lifts in progress
  • Installation of window cleaning equipment at roof floor in progress
  • 93% of drainage and water supply works completed up to the 28th floor and 40% completed between 29th & 31st floor
  • 85% of air conditioning works completed up to 29th floor and 20% completed in 30th floor
  • 80% of fire fighting system completed up to 28th floor
  • 70% of electrical works are completed up to the 29th floor

January 2011 Report

  • 100% of sub structure is complete
  • 100% of super structure is complete
  • 100% of plastering work has been completed up to 28th floor and 50% completed in the 29th floor.
  • 100% of block work has been completed up to 30th floor and 60% completed in the 30th floor.
  • Wall tiling is in progress as per the following percentages;
    Ground floor: 93%.
    Floors 2-10: 87%.
    Floors 12 &13: 75%
    Floors 14-21: 77%
    Floors 22-28: 70%
  • Floor tiling is in progress as per the following percentages:
    Ground floor: 35%
    Floors 14-17: 85%
    Floors 18-24: 80%
    Floors 25-28: 40%
  • Drainage and water supply works are in progress up to the 28th floor; 88% completed.
  • AC works are in progress up to the 29th floor with an average of 75% completion,
  • Fire alarm & emergency cabling is in progress up to the 28th floor with an average of 70% completion.
  • Electrical works are in progress up to the 29th floor with 70% completed.
  • The Curtain walling works progressing as per the following details and percentages:
    Frame work: 72%
    Glass work: 44%
    Aluminium cladding work: 57%

December 2010 Report

  • 100% of sub structure is complete
  • 100% of block work has been completed up to 29th floor and in progress on 30th floor.
  • 100% of plastering work has been completed up to 28th floor and in progress on 29th floor.
  • Wall tiling is in progress as per the following percentage;
  • Ground floor: 85%.
  • Floors 2-10: 80%.
  • Floors 12&13: 68%
  • Floors 14-21: 70%.
  • Floors 22-26: 65%.
  • Floor tiling is in progress as per the following percentage:
  • Floors 14-17: 80%
  • Floors 18-24: 70%
  • 25th Floor: 30%
  • Drainage and water supply works are in progress on the 27th floor; 85% completed.
  • AC works are in progress up to the 24th floor with an average of 77% completion, 55% in 25th and 20% in the 26th floors receptively.
  • Fire alarm & emergency cabling is in progress up to the 26th floor with an average of 70% completion.
  • Electrical works are in progress up to the 29th floor with 64% completed.
  • The Curtain walling work is in progress as per the following percentages:
  • Frame work: 66%
  • Glass work: 35%.
  • Aluminium cladding work: 43%.

November 2010 Report

  • 100% of sub structure is complete.
  • 100% of block work has been completed up to 29th floor and in progress on 30th floor.
  • 100% of plastering work has been completed up to 28th floor and in progress on 29th floor.
  • Wall tiling is in progress from the 20th to the 26th floor.
  • Floor tiling is in progress from the 16th to the 23rd floor.
  • Drainage and water supply works are in progress on the 27th floor; 85% completed.
  • AC works are in progress up to the 24th floor with an average of 70% completed.
  • Fire alarm & emergency cabling work is in progress up to the 26th floor with an average of 65% completed.
  • Electrical works are in progress up to the 29th floor with 60% completed.
  • The Curtain walling works are underway; the aluminum frame works are in progress up to the 28th floor in the rear and front elevations and up to 14th floor in the left and right elevations.
  • The glazing work is in progress up to the 15th floor in the front and rear elevations and up to 7th floor in the left and right elevations.
  • The aluminum cladding works are in progress up to the 15th floor.

October 2010 Report

  • Block works are complete up to 28th floor.
  • Wall plastering works have been completed up to the 27th floor and now in progress in 28th floor.
  • Wall tiling works are complete up to the 19th floor and in progress in floors 20 to 25.
  • Floor tiling works are completed up to the 15th floor and in progress in the 16th and 17th floors.
  • Drainage and water supply works are completed up to the 26th floor and 75% complete on the 27th floor.
  • AC works are completed up to the 22nd floor and in progress on the 23nd floor.
  • Fire alarm & emergency cabling are completed up to the 19th floor and in progress up to the 24th floor.
  • Electrical works are completed up to the 26th floor and in progress up to the 29th floor.
  • The aluminum frame work for the curtain walling work is well advanced having reached the 24th floor on the rear and front elevations and the 12th floor on the left and right elevations.
  • The glazing work has reached the 13th floor on the front and rear elevations and to the 6th floor on the left and right elevations.
  • The aluminum cladding work has reached the 13th floor.

September 2010 Report

  • 100% of the sub-structure is complete.
  • Final approval for the swimming pool works on the 30th floor is expected by 13th September.
  • Wall plastering works are completed up to the 26th floor and now in progress in 27th floor.
  • Wall tiling works are completed up to the 17th floor and in progress in the18th floor.
  • Floor tiling works are completed up to the 14th floor and in progress in the 15th and the 16th floors.
  • Drainage and water supply works are completed up to the 26th floor and in progress in the 27th floor.
  • AC works are completed up to the 21st floor and 80% complete in the 22nd floor.
  • Fire alarm & emergency cabling are completed up to the 18th floor and 40% complete up to the 22nd floor.
  • Electrical works are completed up to the 25th floor and 35% complete up to the 27th floor.
  • Curtain walling works are underway with the aluminum frame work completed up to the 24th floor and the glass is fixed up to the 8th floor and in progress in the 9th and 10th floors.

August 2010 Report

  • The 28th floor slab was cast on 20th July 2010.
  • As per Dubai Municipality regulation and since we have a steel roof and pergola steel structure the design of the last four floors has to be checked and approved by the third party structural engineering office and Dubai Municipality prior to any casting activity for those remaining floors. The third party consultant has already approved the design and now it is with DM for their final review and approval. We are expecting this approval to come through by next week then the contractor needs two days to cast the 29th slab and the cycle will be a slab cast every week.
  • 100% of the block works are completed up to 24th floor.
  • 60% of the block works are completed in the 25th floor.
  • 100% of the plastering works are completed up to the 17th floor and is in progress from the 18th to the 21st.
  • The tiling works are underway; 80% in the toilets and 70% in the kitchens.
  • Drainage and water works are in progress up to the 25th floor.
  • AC ducts are completed from the Ground up to the 17th floor.
  • 100% of fire alarm & emergency cabling works are completed up to the 18th floor and in progress in the 19th floor.
  • 100% of the electrical works are completed up to the 24th floor and in progress in the 25th floor.
  • The Curtain walling works are underway with the aluminum frame works completed up to the 17th floor and the glass is fixed up to the 10th floor; of course the glass works are only in progress on these floors and are not yet 100% complete.
  • The renders and the design work for the main lobby, common areas and the Pure White Health Club have been completed by John R Harris and Partners (JRHP)

July 2010 Report

  • The 26th floor slab was cast on 28/06/2010.
  • The 27th floor slab is expected to be cast on 6/07/2010.
  • Mechanical Electrical and Plumbing works including Air conditioning, Fire fighting and wiring works are in progress up to the 20th floor.
  • Block works have been completed up to the 21st floor;
  • The walls have been plastered up to the 16th floor. ������

June 2010 Report

  • The 23rd floor slab was cast on 2nd June.
  • The steel reinforcement for the core walls CW1, CW2, CW3 and CW4 from 24th floor to U/s 25th were completed on 3rd June.
  • The steel reinforcement for columns & CW5 from 23rd floor to U/s 24th floor were completed on 3rd June.
  • Core walls CW1, CW2 & CW3 & CW4 from 23rd floor to U/s 24th floor will be cast by 10th June.
  • The columns and CW5 from 22nd floor to U/s 23rd floor were cast 1st June.
  • Chasing, conduiting & G.I. box fixing and wiring in progress at 16th floor.
  • Fire alarm wiring completed up to the 19th floor.
  • Lighting control wiring in progress on the 16th floor.
  • Cable tray support fixing completed up to 17th floor.
  • Electrical S/o & lighting control wiring marking down at 16th floor.
  • Drainage in progress at 17th floor.
  • A/C ducting in progress at Ground floor.
  • Chilled water piping in progress at ground floor
  • Chilled water piping pressure test completed up to 3rd floor & and in progress at the 4th & 5th floors.

May 2010 Report

  • The 20th floor slab was cast on 4th May
  • 65% of fire alarm & emergency cabling completed at 12th &13th floors.
  • 85% of electrical lighting wiring one circuit in the corridor completed at 12th &13th floors.
  • Electrical lighting wiring in progress on 2nd to 7th floor.
  • Fire fighting main line is in progress at the 9th floor.
  • Chilled water piping main line in progress at 7th to 8th floor.

April 2010 Report

  • The 16th floor slab was cast on 27th March.
  • The steel reinforcement for the core walls CW1, CW2 & CW3 from 17th floor to U/s 18th floor are complete.
  • The steel reinforcement for columns & CW5 from 16th floor to U/s 17th floor are in progress.
  • The steel reinforcement for CW4 from 17th floor to U/s 18th floor is in progress.
  • Core walls CW1, CW2 & CW3 & CW4 from 16th floor to U/s 17th floor have been cast.
  • The partial area of screen for Basement 2 has been cast.
  • Chasing conduiting & G.I. box fixing in progress on floor 11.
  • G.I boxes and junction box fixing on the core wall has been completed at 12th floor.
  • Fire alarm & emergency cabling completed 80% at 11th floor high level.
  • Electrical and MEP works are in progress and have reached the 10th floor.

* Please note that the details of construction progress for this development are largely provided to us by the project consultants and contractors. Any reference to future construction milestone dates is in accordance with their reports to us and The First Group are unable to accept responsibility for any errors.