Construction Status
August Report
- The permanent power connection was energized on 7/7/2010.
- UNEC and Fawaz the MEP contractors are working in co-ordination with the facility managers (MAB) and are well advanced with the final sign off of the air conditioning, fire fighting system, evacuation system and the swimming pool.
- MAB the facility management company only accept handover of the MEP aspects of the building from the contractors and consultants upon satisfactory completion of testing and commissioning.
- UNEC has completed all the civil works snags in all the units and the common areas; now they are attending to the owner’s snag lists with the whole process carefully controlled and monitored.
July Report
- All cabling works to and from the substation are complete
- Landscaping disturbed by cabling works has been reinstated
- Mains water connection is scheduled for first few days of July
June Report
- The upgrade works on the penthouses are in well advanced and the full works will be completed by end of June.
- Upon power connection:
- Final testing and commissioning will commence most specifically the air conditioning, IT infrastructure and MEP testing.
- Plant and machinery operational handover to facilities manager.
- Reinstatement of landscaping to resolve the disturbance caused by the cable laying
- Commencement of pre-opening deep-cleaning of building.
May Report
- UNEC has completed the final de snagging works.
- DEWA's contractor has started laying the cables; Dubai Sports City has confirmed the works will be completed and power connected in 18 days.
April Report
- The RTA has provided the NOC to Dubai Sports City and Dubai Electricity and Water Authority and DEWAs approved contractor has commenced laying the cables.
- Works to provide permanent power connection are expected to be completed within 8 weeks and every effort is being made by all parties to reduce this timescale.
- UNEC have completed final de snagging works up to the 7th floor.