Construction Status
August Report
- The Mezzanine floor was cast in the week ending 23/07/2010.
- The 1st podium slab is due to be cast by 7th August.
- The final building permit based on the revised structural design has been received from Dubai Municipality.
- The renders and the design of the upgraded units, standard units and common areas have been completed by John R Harris and Partners (JRHP).
July Report
- All the vertical elements for the structure has been cast
- Retaining walls are 100% completed.
- The shuttering and steel work for the Ground floor slab is completed.
- The Ground floor slab was cast on the 30/06/2010
June Report
- Casting of the raft foundation started at 10am on 27th of May and was completed at 4pm 28th May. A total of 4200 cubic metres of cement was used.
- The shuttering and steel works for the Ground’s floor slab has started; expected to pour the concrete at by 30th June.
- The contract documents have been delivered to us for stamping and signing on 31/5/2010.
- The revised Gross Floor Area has been approved by DSC and application submitted to DM on 1st of June for approval.
- The foundations are 100% complete.
May Report
- The steel works are in progress in the lift pit area and this is expected to be cast in mid May.
- 100% of the water proof membrane of the Floor and wall has been completed for the foundation levels.
- 100% of the solid block walls on the 1st & 2nd levels of the foundation has been completed
April Report
- Casting of the P.C.C for the lift pit is complete.
- Two layers of water proofing membrane for the floor and walls of the lift pit area are complete.
- The protection board for the wall and the protection screed for the floor of the lift pit area are complete.
- Casting of the P.C.C for the 1st & 2nd levels on the foundation is completed.
- 40% of the water proof membrane of the (Floor and wall) has been completed for the foundation levels.
- The Pile head treatment is complete.
- 85% of the solid block wall is in progress for the 1st & 2nd levels on the foundation.
- All levelling and compaction works have been completed.
- Casting of the P.C.C for the water tanks is complete.