Construction History

March 2012

The Spirit

February 2012

The Spirit

January 2012

The Spirit

December 2011

The Spirit

November 2011

The Spirit

October 2011

The Spirit

September 2011

The Spirit

August 2011

The Spirit

July 2011

The Spirit

June 2011 Report

    Block works

  • For the full building 100%

    Plastering works

  • From B3 to 18th floor 100%
  • Progress in Mechanical floor 100%

    Ceramic tiling for bathrooms walls

  • Progress in 1st to 12th floor 100%
  • Progress from 13th to 18th floor 90% Ceramic tiling for bathrooms walls

    Ceramic tiling for dry & wet area floors (inside flats only)

  • Progress from 1st floor to 16th floor 98%
  • Progress in 17th &18th floor 75%

    Bath tub installation

  • Progress from 1st floor to 18th floor (including testing) 100%

    Waterproofing works

  • Progress from 1st floor to 18th floor (including testing) 100%

    False ceiling works Gypsum board (inside flat only)

  • Progress from 1st to 14th floor 80%
  • Progress in 15th floor 45%

    False ceiling works Wooden panels (inside flat only)

  • Progress from 1st to 14th floor 80%
  • Progress in 15th floor 45%

    Painting works

  • Progress from 1st to 4th floor (Stucco layer only) 90%
  • Progress in 5th floor 60%

    Aluminum & Curtain wall works

  • Installation of façade structural frame (in process) 75%
  • Installation of curtain wall glass (in process) 65%
  • Installation of Aluminum cladding (in process) 60%

    Kerbstone & Wheel stopper works

  • Progress in B3 & B2 100%
  • Progress in B1 100%

    Roof & Upper Roof Waterproofing

  • Roof: 100%
  • Upper Roof: 100%
  • Lifts works: 75%
  • MEP works: (AC, drainage, water pipes, sewerage and firefighting) are in progress up to the 18th floor with an average of 73%.

May 2011 Report

  • 100% of the sub-structure is complete.
  • 100% of super structure is complete
  • 100% of block work is complete
  • 100% of plaster work is completed up to the 18th floor in the mechanical floor
  • 98% of ceramic tiling for bathroom walls is complete up to 11th floor and 90% progressed from floors 12 to 18
  • 98% of ceramic tiling for wet and dry in apartments is complete to the 16th floor with 50% complete in the 17th floor
  • 100% of bathtubs have been installed and tested up to 18th floor
  • 100% of waterproofing works including testing completed up to 18th floor
  • 80% of false ceiling works by way of suspension frame plus gypsum board inside apartments are complete up to 14th floor and 30% complete in 15th floor
  • 30% of stucco layer painting works completed up to 16th floor and 15% complete in 17th floor
  • 75% of façade structural frame installation complete
  • 60% of curtain wall glass installation complete 18%
  • 50% of Aluminium cladding installation complete
  • 100% of kerbstone & wheel stopper works completed in all basements
  • 100% of roof and upper roof waterproofing completed
  • 50% of Lift installation works completed
  • MEP works (AC, drainage, water pipes, sewerage and fire fighting) are on average 65% complete up to the 18th floor.

April 2011 Report

  • 100% of the sub-structure is complete.
  • 100% of super structure is complete
  • 100% of block work is complete
  • 97% of plaster work is completed up to the 18th floor and 90% completed in the mechanical floor
  • 98% of ceramic tiling for bathroom walls is complete up to 10th floor and 80% progressed from floors 11 to 18
  • 98% of ceramic tiling for wet and dry in flats is complete to the 15th floor with 50% complete in the 16th floor
  • 100% of bathtubs have been installed and tested up to 17th floor with 50% complete in 18th floor
  • 100% of waterproofing works including testing completed up to 18th floor
  • 70% of false ceiling works by way of suspension frame plus gypsum board inside flats are complete up to 11th floor and 50% complete in 12th floor
  • 30% of stucco layer painting works completed up to 15th floor and 15% complete in 16th floor
  • 70% of façade structural frame installation complete
  • 50% of curtain wall glass installation complete 18%
  • 40% of Aluminium cladding installation complete
  • 100% of kerbstone & wheel stopper works completed in all basements
  • 100% of roof and upper roof waterproofing completed
  • 10% of Lift installation works completed
  • MEP works (AC, drainage, water pipes, sewerage and fire fighting) are on average 55% complete up to the 18th floor.

March 2011 Report

  • 100% of the sub-structure is complete.
  • 100% of super structure is complete.
  • 100% of block work is completed up to the 18th floor and 95% completed in the mechanical floor.
  • 95% of plaster work is completed up to the 18th floor and 10% completed in the mechanical floor.
  • 98% of ceramic tiling for bathroom walls is in progress up to 5th floor, 80% complete in 6th to 17th floor and 10% in progress on 18th floor.
  • 98% of ceramic tiling for wet and dry in flats is complete to the 9th floor with 80% complete in the 10th floor and 10% complete in 11th floor.
  • 100% of bathtubs have been installed and tested up to 12th floor with 10% complete in 13th floor.
  • 100% of waterproofing works including testing completed up to 13th floor and 10% complete in 14th floor.
  • 50% of false ceiling works by way of suspension frame plus gypsum board inside flats are complete up to 11th floor and 40% complete in 12th floor.
  • 30% of stucco layer painting works completed up to 11th floor and 15% complete in 12th floor.
  • 35% of facade structural frame installation complete.
  • 40% of curtain wall glass installation complete.
  • 18% of Aluminium cladding installation complete.
  • 100% of kerbstone & wheel stopper works completed in Basements 2 & 3 and 95% completed in Basement1.
  • 100% of upper roof waterproofing completed with 50% completed on roof.

February 2011 Report

  • 100% of the sub-structure is complete.
  • 100% of super structure is complete
  • 100% of block work is completed up to the 18th floor and 70% completed in the mechanical floor
  • 95% of plaster work is completed up to the 17th floor and in 80% completed in 18th floor 80%
  • 98% of ceramic tiling for bathroom walls is in progress up to 3rd floor, 80% complete in floors 4th to 14th floors and 60% in 15th floor
  • 98% of ceramic tiling for wet and dry in flats is complete with 80% complete in the 8th floor 98%
  • Progress from 4th to 14th floors 80%
  • Progress in 15th floor 60%
  • 100% of bathtubs have been installed up to 8th floor and tested with 10% complete in 9th floor
  • 100% of waterproofing works including testing completed up to 10th floor
  • 50% of false ceiling works by way of suspension frame plus gypsum board inside flats only are complete up to 7th floor and 25% complete up to 8th floor
  • 30% of stucco layer painting works completed up to 10th floor and 15% complete in 11th floor
  • 35% of facade structural frame installation complete
  • 18% of curtain wall glass installation complete 18%
  • 5% of Aluminium cladding installation complete 5%
  • 100% of kerbstone & wheel stopper works Completed in Basements 2 & 3 and 80% completed in Basement1

January 2011 Report

  • 100% of the sub-structure is complete.
  • The 20th floor slab (swimming pool floor) was cast on 30/12/2010 to top out the building.
  • 100% of block work is completed up to the 18th floor.
  • 100% of Plaster work is completed up to the 16th floor.
  • Painting works are in progress as follows as follows:
    B3 Ceiling: 100%; walls: 100%
    B2 Ceiling: 100%: walls: 100%
    B1 Ceiling: 100%: walls: 100%
  • Primer painting: 100% completed up to the 7th floor. Stucco paint (finish paint): 40% completed up to the 5th floor.
  • Tiling works are in progress as follows as follows:
    Floor tiling on floors 1 -3: 100% complete
    Wall tiling on floors 1-12: 40% complete
  • MEP works (AC, drainage, water supply, fire fighting& electrical) are in progress as per the following percentages:
    Floors Ground-5: 75%
    Floors 6-18: 55%

December 2010 Report

  • 100% of the sub-structure is complete.
  • The 19th floor slab (mechanical floor) was cast on 14/11/2010.
  • The 20th floor slab to top out (swimming pool floor) is expected to be cast on 25/12/2010 (delay encountered for DM final approval on the structure).
  • Block works are 100% completed up to the 15th floor, 90% in the 16th and 10% in the 17th floor.
  • Plastering works 100% are completed up to the 12th floor, 75% in 13th floor and 20% in 14th floor.
  • Painting works are in progress as follows:
  • B3 Ceiling: 100%; walls: 100%
  • B2 Ceiling: 90%: walls: 90%
  • B1 Ceiling: 65%: walls: 90%
  • MEP works (AC, drainage, water supply, fire fighting& electrical) are in progress as per the following percentage:
  • Ground-5th floor: 70%.
  • 6-18th floor: 48%.

November 2010 Report

  • 100% of the sub-structure is complete.
  • The 19th floor slab (mechanical floor) will be casted on 14/11/2010.
  • The building will be topped out on 25/11/10 when the 20th floor slab (swimming pool floor) is expected to be cast.
  • Block works are completed up to the 14th floor, 80% in the 15th floor and 10% in the 16th floor.
  • Plastering works are completed up to the 10th floor and 50% in the 11th floor.
  • Painting works are in progress as follows:
    - Basement 3: Ceiling: 85%; walls: 85%
    - Basement 2: Ceiling: 85%: walls: 85%
    - Basement 1: Ceiling: 65%: walls: 65%
  • MEP works (AC, drainage, water supply, fire fighting & electrical) are in progress as follows:
    - Ground - 5th floor 60% complete.
    - 6th � 18th floor 40% complete.

October 2010 Report

  • 100% of the sub-structure is complete.
  • The 17th floor slab was cast on 29th September.
  • The 18th floor slab is expected to be cast on 12th October.
  • Block works 100% completed up to the 12th floor and 60% complete on the 13th floor.
  • Plastering works are completed up to the 7th floor and 50% in the 8th floor.
  • MEP works (AC, drainage, water supply, fire fighting & electrical) are in progress with 60% completed from the ground to 2nd floors, 40% completed from the 3rd to 8th floors and 20% complete between the 9th and 15th floors.

September 2010 Report

  • 100% of the sub-structure is complete.
  • The contractor (UNEC) is 15 days ahead of their programme.
  • The 15th floor slab was cast on 8th September 2010.
  • Block works are completed up to the 10th floor, 85% complete in the 11th and 25% complete in the 12th floors respectively.
  • Plastering works are completed up to the 6th floor and 90% complete in the 7th floor.
  • MEP works (AC, drainage, water supply, fire fighting & electrical) are in progressing with 60% complete from the ground to 2nd floor and 30% complete from the 3rd to 8th floors.

August 2010 Report

  • The contractor (UNEC) is 17 days ahead of their program.
  • The 12th floor was cast on 2/08/2010.
  • The 13th slab is scheduled to be cast on 12th of August, 2010.
  • 100% of the block work has been completed in all the basements (B1, B2 and B3)
  • Block works are underway in 8th and 9th floor
  • Plastering work are underway in the GF & 3rd Floor
  • MEP works are underway in the basements and up to the typical floors
  • Finishing layers of anti carbonation paint completed in B3
  • Levelling layers of paint work completed in B2
  • Primer paint and base coat paint work is complete in B1
  • The 4th Floor is being prepared for plaster works
  • Preparations and MEP works for the new mock up flat No. 7
  • The renderings and the design of the upgraded units, standard units, main lobby and common areas have been completed by jrhp.
  • Preparations for paint finishing sample in B3 level
  • General cleaning in B1 level.

July 2010 Report

  • The 9th floor slab was cast on 19/06/2010
  • Block works in progress:
    - 90% complete at Ground Floor
    - 65% complete at 1st Floor
  • Block work layouts in progress:
    - 55% complete at 2nd Floor
    - 35% complete at 3rd Floor
    - 35% complete at 4th Floor
  • Mechanical, Electrical and Plumbing works underway for all 3 basements and typical floors
    - Painting with Stucco layer in progress
    - 90% complete in Basement 3
  • 70% complete in Basement 2
  • 85% of the plastering work for the stair case from GF to 1st floor is complete.
  • Casting of the 10th floor slab is scheduled for the 10th of July. �

June 2010 Report

  • Casting of the 6th floor slab was done on 30th of May.
  • Steel and shuttering for walls and columns (6th to 7th) slab level is in progress.
  • Block works at Ground Floor are 80% complete.
  • Block works on 1st floor are 25% complete
  • Block work layout for 2nd floor is in progress.
  • Steel and shuttering work for the core wall (5th to 6th) slab level
  • MEP works underway for all 3 basements
  • Painting with Stucco layer in Basement 3 is 60% complete
  • Painting with Stucco layer in B2 level is 30% complete
  • Plastering work for the stair case from GF to 1st floor is 60% complete.

May 2010 Report

  • The contractor is 17 days ahead of his program.
  • The 3rd floor has been casted on 28/04/2010
  • The 4th floor slab is expected to be cast on 08/05/2010.
  • Block works have been completed 100% in B3, 80% in B2 & 50% in B1.
  • Preparations for paint finishing sample in B3 level.
  • General cleaning in B1 level.

April 2010 Report

  • The contractor is 16 days ahead of his program.
  • The 1st floor slab will be cast on 6/4/2010.
  • Steel and shuttering work then pouring concrete for the boundary walls
  • Pouring concrete for the Attic slab
  • Pouring concrete for the stair case in the core zone
  • De shuttering works for the Ground Floor slab is on going.
  • Steel and post tension work for the First Floor slab
  • B-3 preparation for Block Layout

* Please note that the details of construction progress for this development are largely provided to us by the project consultants and contractors. Any reference to future construction milestone dates is in accordance with their reports to us and The First Group are unable to accept responsibility for any errors.