Construction Status
August Report
- The contractor (UNEC) is 17 days ahead of their program.
- The 12th floor was cast on 2/08/2010.
- The 13th slab is scheduled to be cast on 12th of August, 2010.
- 100% of the block work has been completed in all the basements (B1, B2 and B3)
- Block works are underway in 8th and 9th floor
- Plastering work are underway in the GF & 3rd Floor
- MEP works are underway in the basements and up to the typical floors
- Finishing layers of anti carbonation paint completed in B3
- Levelling layers of paint work completed in B2
- Primer paint and base coat paint work is complete in B1
- The 4th Floor is being prepared for plaster works
- Preparations and MEP works for the new mock up flat No. 7
- The renderings and the design of the upgraded units, standard units, main lobby and common areas have been completed by jrhp.
- Preparations for paint finishing sample in B3 level
- General cleaning in B1 level.
July Report
- The 9th floor slab was cast on 19/06/2010
- Block works in progress:
- 90% complete at Ground Floor
- 65% complete at 1st Floor - Block work layouts in progress:
- 55% complete at 2nd Floor
- 35% complete at 3rd Floor
- 35% complete at 4th Floor - Mechanical, Electrical and Plumbing works underway for all 3 basements and typical floors
- Painting with Stucco layer in progress
- 90% complete in Basement 3 - 70% complete in Basement 2
- 85% of the plastering work for the stair case from GF to 1st floor is complete.
- Casting of the 10th floor slab is scheduled for the 10th of July.
June Report
- Casting of the 6th floor slab was done on 30th of May.
- Steel and shuttering for walls and columns (6th to 7th) slab level is in progress.
- Block works at Ground Floor are 80% complete.
- Block works on 1st floor are 25% complete
- Block work layout for 2nd floor is in progress.
- Steel and shuttering work for the core wall (5th to 6th) slab level
- MEP works underway for all 3 basements
- Painting with Stucco layer in Basement 3 is 60% complete
- Painting with Stucco layer in B2 level is 30% complete
- Plastering work for the stair case from GF to 1st floor is 60% complete.
May Report
- The contractor is 17 days ahead of his program.
- The 3rd floor has been casted on 28/04/2010
- The 4th floor slab is expected to be cast on 08/05/2010.
- Block works have been completed 100% in B3, 80% in B2 & 50% in B1.
- Preparations for paint finishing sample in B3 level.
- General cleaning in B1 level.
April Report
- The contractor is 16 days ahead of his program.
- The 1st floor slab will be cast on 6/4/2010.
- Steel and shuttering work then pouring concrete for the boundary walls
- Pouring concrete for the Attic slab
- Pouring concrete for the stair case in the core zone
- De shuttering works for the Ground Floor slab is on going.
- Steel and post tension work for the First Floor slab
- B-3 preparation for Block Layout