Construction Status

August Report

  • The contractor (UNEC) is 17 days ahead of their program.
  • The 12th floor was cast on 2/08/2010.
  • The 13th slab is scheduled to be cast on 12th of August, 2010.
  • 100% of the block work has been completed in all the basements (B1, B2 and B3)
  • Block works are underway in 8th and 9th floor
  • Plastering work are underway in the GF & 3rd Floor
  • MEP works are underway in the basements and up to the typical floors
  • Finishing layers of anti carbonation paint completed in B3
  • Levelling layers of paint work completed in B2
  • Primer paint and base coat paint work is complete in B1
  • The 4th Floor is being prepared for plaster works
  • Preparations and MEP works for the new mock up flat No. 7
  • The renderings and the design of the upgraded units, standard units, main lobby and common areas have been completed by jrhp.
  • Preparations for paint finishing sample in B3 level
  • General cleaning in B1 level.

July Report

  • The 9th floor slab was cast on 19/06/2010
  • Block works in progress:
    - 90% complete at Ground Floor
    - 65% complete at 1st Floor
  • Block work layouts in progress:
    - 55% complete at 2nd Floor
    - 35% complete at 3rd Floor
    - 35% complete at 4th Floor
  • Mechanical, Electrical and Plumbing works underway for all 3 basements and typical floors
    - Painting with Stucco layer in progress
    - 90% complete in Basement 3
  • 70% complete in Basement 2
  • 85% of the plastering work for the stair case from GF to 1st floor is complete.
  • Casting of the 10th floor slab is scheduled for the 10th of July.  

June Report

  • Casting of the 6th floor slab was done on 30th of May.
  • Steel and shuttering for walls and columns (6th to 7th) slab level is in progress.
  • Block works at Ground Floor are 80% complete.
  • Block works on 1st floor are 25% complete
  • Block work layout for 2nd floor is in progress.
  • Steel and shuttering work for the core wall (5th to 6th) slab level
  • MEP works underway for all 3 basements
  • Painting with Stucco layer in Basement 3 is 60% complete
  • Painting with Stucco layer in B2 level is 30% complete
  • Plastering work for the stair case from GF to 1st floor is 60% complete.

May Report

  • The contractor is 17 days ahead of his program.
  • The 3rd floor has been casted on 28/04/2010
  • The 4th floor slab is expected to be cast on 08/05/2010.
  • Block works have been completed 100% in B3, 80% in B2 & 50% in B1.
  • Preparations for paint finishing sample in B3 level.
  • General cleaning in B1 level.

April Report

  • The contractor is 16 days ahead of his program.
  • The 1st floor slab will be cast on 6/4/2010.
  • Steel and shuttering work then pouring concrete for the boundary walls
  • Pouring concrete for the Attic slab
  • Pouring concrete for the stair case in the core zone
  • De shuttering works for the Ground Floor slab is on going.
  • Steel and post tension work for the First Floor slab
  • B-3 preparation for Block Layout